5 weeks in. Seems a lot has gone on, and can’t really remember the first couple of weeks!
In this timeframe, we’ve:-
- Removed headlining and insulated cab (see HERE ) . Right b*tch of a job…
- Built main walls and fixed to bonded battens
- Part built garage – habitation walls
- Checked everything fits (!)
- Completed garage floor
- Modified gas locker from square to cheese shaped to fit in rear corner
- Installed leisure batteries (affixed with load hooks with load spreaders underneath)
- Installed diesel heater (not commissioned)
- Installed primary wiring looms
- Installed mains charger (not commissioned) and battery to battery system (not yet connected)
- And installed one skylight (2 more to go). I thin that was week 3 lol